Thursday, 18 August 2011
Headland Park - Environment Monitoring and Fence Upgrade
Laing O'Rourke, on behalf of the Barangaroo
Delivery Authority, is planning to capture baseline information
about air quality, background noise and vibration levels.
This will ensure that when construction starts, the levels can be
effectively measured and reported.
Subject to Council approval, there will be
monitors at the locations indicated in the attached map. The
monitors are small in size and will have minimal visual impact,
however you may notice them in the area.
As part of the upgrade of the Barangaroo
perimeter fence, Laing O'Rourke currently has an application in
with Council regarding a replacement fence along Merriman Street.
This will be in similar chain wire to what currently exists and
will help to ensure resident and pedestrian safety throughout the
construction period.
Pending approval and weather permitting, this
work is anticipated to take place over a number of days later in
April. Hours of work are 7am - 6pm Monday to Friday and 8am -
3pm Saturday. The equipment being used includes delivery trucks and
hand tools. Noise levels are predicted to remain within
allowable levels.
In order to ensure safe pedestrian access
during construction hours, there will be temporary changes to local
traffic conditions including short-term occupation of some parking
spaces on the Headland Park side of Merriman Street. Traffic
control measures will be in place throughout this time.